[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92379":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92379,64,1,"单选题","在建设工程风险管理过程中，风险识别最后一步是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制工程风险清单",true,{"key":16,"text":17,"correct":18},"B","建立初步清单",false,{"key":20,"text":21,"correct":18},"C","风险归集和分类",{"key":23,"text":24,"correct":18},"D","收集和整理相关信息资料","工程风险识别是风险管理的第一步，能否将工程潜在的重大风险都识别出来，决定了风险管理效果。可按下列步骤进行工程风险识别：①收集和整理相关信息资料；②建立工程风险初始清单；③进行风险归集和分类；④编制工程风险清单。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]