[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92375":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92375,64,1,"单选题","下列内容中，不属于风险估计内容的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","风险事件发生的可能性估计",false,{"key":16,"text":17,"correct":14},"B","风险事件产生的后果估计",{"key":19,"text":20,"correct":21},"C","风险责任分配估计",true,{"key":23,"text":24,"correct":14},"D","风险事件影响范围估计","工程风险估计是建立在有效识别工程风险的基础上，运用概率论和数理统计方法，对工程建设各阶段的风险事件发生的可能性、可能产生的后果、影响范围和可能发生的时间等进行估计，即其内容包括：①风险事件发生的可能性估计；②风险事件产生的后果估计；③风险事件影响范围估计；④风险事件发生的时间估计。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]