[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92370":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},92370,64,2,"多选题","根据下表中工作之间的逻辑关系绘制的双代号网络图如下图所示，其绘图错误有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","逻辑关系不正确",true,{"key":16,"text":17,"correct":14},"B","有多个终点节点",{"key":19,"text":20,"correct":21},"C","有多个起点节点",false,{"key":23,"text":24,"correct":14},"D","节点编号有错误",{"key":26,"text":27,"correct":21},"E","有多余的虚工作","ABD","A项，逻辑关系不正确。网络图必须按照已定的逻辑关系绘制，这是正确表达各项工作之间逻辑关系的基本保证。本图中逻辑使得E的紧前工作只有B，工作F的紧前工作多了B。B项，有多个终点节点。网络图中应只有一个起点节点和一个终点节点（任务中部分工作需要分期完成的网络计划除外）。除网络图的起点节点和终点节点外，不允许出现没有外向箭线的节点和没有内向箭线的节点。本图中，终点节点有⑥、⑧两个。D项，节点编号有错误。网络图中的节点都必须有编号，其编号严禁重复，并应使每一条箭线上箭尾节点编号小于箭头节点编号。本图中，③—②和⑦—⑥的虚工作节点编号有误，其箭头节点小于箭尾节点的编号。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]