[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92369":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92369,64,1,"单选题","下列与工程有关的因素中，属于厘定建筑工程保险费率的主要因素是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建筑工程工期",false,{"key":16,"text":17,"correct":14},"B","保险公司的承保能力",{"key":19,"text":20,"correct":21},"C","承包人经营管理水平",true,{"key":23,"text":24,"correct":14},"D","工程项目的总概算","厘定建筑工程保险费率主要考虑以下因素：保险责任范围大小；工程本身的危险程度；承包人及其他工程关系方的资信、经营管理水平及经验等条件；保险人以往承保同类工程的损失记录；工程免赔额的高低及第三者责任和特种风险的赔偿限额。故选项C正确。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]