[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92359":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92359,64,1,"单选题","由于通货膨胀、外汇浮动、物价上涨与价格调整而产生的工程项目风险属于（）方面的风险。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","政治",false,{"key":16,"text":17,"correct":18},"B","经济",true,{"key":20,"text":21,"correct":14},"C","工程",{"key":23,"text":24,"correct":14},"D","管理","经济风险包括：宏观形势不利，投资环境差劣，市场物价不正常上涨，通货膨胀幅度过大，投资回收期长，基础设施落后，资金筹措困难。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]