[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92354":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},92354,64,2,"多选题","某工程项目的双代号时标网络计划如下图所示，项目进行到第6周周末时，检查了实际进度并绘制出实际进度前锋线。关于工作进度对工期影响的说法，正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作B将使工期拖延3周",false,{"key":16,"text":17,"correct":14},"B","工作C将使工期拖延1周",{"key":19,"text":20,"correct":21},"C","工作D将使工期拖延2周",true,{"key":23,"text":24,"correct":21},"D","工作C不影响工期和紧后工作",{"key":26,"text":27,"correct":21},"E","工作B将使工期拖延2周、紧后工作最早开始时间推迟3周","CDE","选项A中：工作B拖后了3周，因为它没有自由时差，所以它使其紧后工作的最早开始时间推迟3周，但因为工作B有1周总时差所以并没有使工期拖延3周，而是拖延2周。故选项A错误。选项B中：工作C只是拖延了1周，又因为有1周的自由时差，所以C工作不影响其紧后工作的最早开始时间，更不影响总工期。故选项B错误。选项C中：工作D为关键工作，它拖后了2周，将使总工期拖延2周。故选项C正确。选项D和选项E的说法正确。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]