[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92325":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},92325,64,2,"多选题","某工程项目的单代号网络计划如下图所示，其关键工作有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作B",true,{"key":16,"text":17,"correct":14},"B","工作C",{"key":19,"text":20,"correct":21},"C","工作D",false,{"key":23,"text":24,"correct":21},"D","工作F",{"key":26,"text":27,"correct":14},"E","工作H","ABE","用标号追踪法，我们可以得出关键线路有两条，分别是工作A—工作B—工作E—工作H—工作I和工作A—工作C—工作E—工作G—工作I。其中关键工作有工作A、工作B、工作C、工作E、工作G、工作H和工作I共七项。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]