[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92317":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92317,64,1,"单选题","由于承包人原因造成某项缺陷或损坏使某项工程设备不能按原定目标使用而需要再次检查、检验和修复的，发包人有权要求承包人相应延长缺陷责任期，但缺陷责任期最长不超过（）年。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","5","由于承包人原因造成某项缺陷或损坏使某项工程设备不能按原定目标使用而需要再次检查、检验和修复的，发包人有权要求承包人相应延长缺陷责任期。但缺陷责任期最长不超过2年。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]