[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92312":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},92312,64,2,"多选题","某工程项目的单代号网络计划如下图所示，其关键工作有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作B",true,{"key":16,"text":17,"correct":14},"B","工作C",{"key":19,"text":20,"correct":21},"C","工作D",false,{"key":23,"text":24,"correct":21},"D","工作F",{"key":26,"text":27,"correct":14},"E","工作H","ABE","此题考查单代号网络计划中关键工作的确定。利用相邻两项工作之间的时间间隔确定关键线路：从网络计划的终点节点开始，逆着箭线方向依次找出相邻两项工作之间时间间隔为零的线路就是关键线路。相邻两项工作之间的时间间隔是指其紧后工作的最早开始时间与本工作最早完成时间的差值。通过计算相邻两项工作之间的时间间隔，逆着箭线方向依次找出相邻两项工作之间时间间隔为零的线路有两条，分别为A—B—E—H—I和A—C—E—G—I，其中关键工作有A、B、C、E、G、H和I七项。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]