[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92291":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92291,64,1,"单选题","在建设工程风险管理过程中，风险识别操作的起点是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确认不确定性的客观存在",false,{"key":16,"text":17,"correct":18},"B","建立初步清单",true,{"key":20,"text":21,"correct":14},"C","确定各种风险事件并推测其结果",{"key":23,"text":24,"correct":14},"D","制定风险预测图","在建设工程风险管理过程中，风险管理的第一步是风险识别，风险识别的第一步是确认不确定性的客观存在，但风险识别的操作起点是建立初步清单。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]