[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92223":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92223,64,1,"单选题","在购买了安装工程保险后，在保险期内由于电气超负荷引起的损失及费用，保险人应( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","对由此原因造成的任何损失都不负责任",false,{"key":16,"text":17,"correct":14},"B","只对由此原因造成的电气设备或电气用具本身的损失予以赔偿",{"key":19,"text":20,"correct":21},"C","只对由此原因造成的电气设备或电气用具以外的其他保险财产损失予以赔偿",true,{"key":23,"text":24,"correct":14},"D","对电气设备或电气用具及其他保险财产损失均予以赔偿","此题考查安装工程一切险除外责任。由于超负荷、超电压、碰线等电气原因造成电气设备或电气用具本身的损失，安装工程一切险不予负责，只对由于电气原因造成的其他保险财产的损失予以赔偿。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]