[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92197":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92197,64,1,"单选题","工程风险识别常用的方法不包括( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","核对表法",false,{"key":16,"text":17,"correct":14},"B","头脑风暴法",{"key":19,"text":20,"correct":14},"C","常识、经验和判断法",{"key":22,"text":23,"correct":24},"D","蒙特卡洛法",true,"此题考查工程风险识别常用方法。工程风险识别需要借助一些分析方法进行更多系统的横向思考。借助这些方法，可提高风险识别效率，操作规范，且不容易产生遗漏。在实际应用中可结合工程项目具体情况，组合使用这些方法：①核对表法；②头脑风暴法；③常识、经验和判断法。选项D属于工程风险评价常用的方法。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]