[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92191":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92191,64,1,"单选题","将工程风险分为高度、中度、低度风险的依据是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","风险造成的后果",false,{"key":16,"text":17,"correct":14},"B","风险发生的原因",{"key":19,"text":20,"correct":21},"C","风险作用的强度",true,{"key":23,"text":24,"correct":14},"D","风险是否可管理","此题考查工程风险分类。工程风险是指工程项目在决策、设计、施工及竣工验收等阶段可能遭受的风险。为便于识别风险和对不同类型风险采取不同的分析方法和应对措施，可按不同原则和标准，对工程风险进行分类。其中，按风险作用的强度可以分为高度风险、中度风险和低度风险。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]