[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92183":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},92183,64,1,"单选题","在工程风险监控时发现一些新的风险产生时，就要能随机应变，及时提出应对措施，这属于工程风险控制的( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","权变措施",true,{"key":16,"text":17,"correct":18},"B","纠正措施",false,{"key":20,"text":21,"correct":18},"C","项目变更申请",{"key":23,"text":24,"correct":18},"D","项目变更建议","此题考查工程风险控制措施。在风险监视的基础上，应针对发现的问题，及时采取风险控制措施。这些措施包括：权变措施、纠正措施，以及提出项目变更申请或建议等，并对工程风险重新进行评估，对风险应对计划作出调整。其中，权变措施是指未事先计划或考虑到的应对风险措施。工程项目是一个开放性系统，实施环境复杂，有许多风险因素在编制风险计划时是考虑不到的，或者对其没有充分认识。在工程风险监控时发现某些风险的严重性或者是有一些新的风险产生时，就要能随机应变，及时提出应对措施，并将其纳入项目和风险应对计划中。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]