[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92179":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92179,64,1,"单选题","工程建设参与方有意识地选择自己承担风险后果的一种风险应对策略是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","风险转移",false,{"key":16,"text":17,"correct":14},"B","风险预防",{"key":19,"text":20,"correct":21},"C","风险自留",true,{"key":23,"text":24,"correct":14},"D","风险利用","此题考查风险应对策略。风险自留是指工程建设参与方有意识地选择自己承担风险后果的一种风险应对策略。风险自留是一种风险财务技术，工程建设参与方明知可能会发生风险事件，但在权衡各种风险应对策略后，从经济性和可行性考虑，仍将风险自留，当风险损失出现时，则需要依靠工程建设参与方自身财力去弥补。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]