[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92175":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92175,64,1,"单选题","工程风险减轻的途径不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","减少风险发生概率",false,{"key":16,"text":17,"correct":18},"B","把风险转移出去",true,{"key":20,"text":21,"correct":14},"C","分散风险",{"key":23,"text":24,"correct":14},"D","分离风险","此题考查风险减轻途径。风险减轻是指将工程风险发生的概率或后果降低到某一可接受程度。在制定风险减轻措施时，必须依据工程风险特性，尽可能将工程风险降低到可接受水平，常见途径有减少风险发生概率、减少风险事件造成的损失、分散风险、分离风险等。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]