[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92162":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},92162,64,1,"单选题","建立建设工程初始风险清单的有效途径是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","采用保险公司公布的潜在损失一览表",false,{"key":16,"text":17,"correct":14},"B","采用风险管理学会公布的潜在损失一览表",{"key":19,"text":20,"correct":14},"C","采用风险管理协会公布的潜在损失一览表",{"key":22,"text":23,"correct":24},"D","通过适当的风险分解方式来识别风险",true,"此题考查工程风险识别相关内容。通过适当的风险分解方式来识别风险是建立工程风险初始清单的有效途径。对于大型复杂工程项目，首先应按单项工程、单位工程进行分解，从时间、目标和因素等维度对各单项工程和单位工程进行分解后，可以较容易地识别出工程项目主要的常见风险。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]