[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92154":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92154,64,1,"单选题","综合考虑工程项目各风险之间的相互影响、相互作用，以及对工程项目的总体影响，然后与风险评价基准比较，确定是否采取控制措施的过程是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","风险识别",false,{"key":16,"text":17,"correct":14},"B","风险估计",{"key":19,"text":20,"correct":21},"C","风险评价",true,{"key":23,"text":24,"correct":14},"D","风险应对","此题考查工程风险评价。风险评价是指在风险识别和风险估计的基础上，综合考虑工程项目各风险之间的相互影响、相互作用，以及对工程项目的总体影响，然后与风险评价基准进行比较，确定是否要对工程项目采取控制措施的过程。通过工程风险评价，可进一步认识已估计的风险发生概率和引起的损失，降低风险估计中的不确定性。当发现原估计和现状出入较大时，可根据工程进展状况，重新估计风险发生概率和可能的后果。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]