[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92114":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92114,64,1,"单选题","以下内容不属于BIM 5D模型的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建筑构件信息",false,{"key":16,"text":17,"correct":14},"B","进度信息",{"key":19,"text":20,"correct":21},"C","质量信息",true,{"key":23,"text":24,"correct":14},"D","预算信息","3D信息模型与预算模型、进度计划集成扩展成为BIM 5D模型，BIM 5D模型包括：①建筑构件信息；②进度信息；③WBS信息；④预算信息及其相互关联关系。基于5D的施工信息模型可自动计算任意时间段、任意WBS节点或任意施工流水段的工程量及相应施工进度的人力、材料、机械消耗量和预算成本，进行工程量计划完成、资源计划平衡和方案优化等施工，5D动态模拟和优化工作。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]