[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92048":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},92048,64,1,"单选题","以下不属于BIM技术应用于施工现场临时设施规划流程的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","标准化族库建立",false,{"key":16,"text":17,"correct":14},"B","主体模型简化",{"key":19,"text":20,"correct":21},"C","垂直运输模拟",true,{"key":23,"text":24,"correct":14},"D","平面布置模拟","此题考查基于BIM的施工现场临时实施规划的流程。应用BIM技术协调施工现场临时设施规划，主要是为解决多阶段平面布置协调中依靠二维图纸堆叠查看的复杂和各阶段平面布置信息不连续问题。其流程主要有：①标准化族库建立；②主体模型简化；③模型信息建立；④平面布置模拟；⑤模型信息使用。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]