[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-92042":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},92042,64,1,"单选题","不属于BIM技术应用于施工进度计划编制流程的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","WBS施工任务分解",false,{"key":16,"text":17,"correct":18},"B","施工进度跟踪分析",true,{"key":20,"text":21,"correct":14},"C","数据接口集成",{"key":23,"text":24,"correct":14},"D","形成4D进度计划","此题考查基于BIM的施工进度计划编制流程。基于BIM的施工进度计划编制，第一步是建立工作分解结构（WBS），然后将WBS作业进度、资源等信息与BIM模型图元信息链接，即可实现4D进度计划，其中的关键是数据接口集成。而施工进度跟踪分析属于基于BIM的施工进度跟踪分析阶段。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]