[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91793":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},91793,64,1,"单选题","装配式混凝土建筑工程成本相比传统现浇方式增加的有（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","机械费",true,{"key":16,"text":17,"correct":18},"B","砌筑工程费",false,{"key":20,"text":21,"correct":18},"C","措施费",{"key":23,"text":24,"correct":18},"D","抹灰工程费","本题考查装配式建筑相比传统现浇方式建筑的差别。造成装配式混凝土建筑工程建造方式成本增加的因素有预制构件产品和运输费用、预制构件吊装费用、机械费用、墙板和楼板拼缝处理及相关材料费用。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]