[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91518":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},91518,64,1,"单选题","招标的准备工作不包括（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","需要履行项目审批手续的，已经履行审批手续",false,{"key":16,"text":17,"correct":14},"B","资金来源已经落实",{"key":19,"text":20,"correct":14},"C","有满足工程招标需要的设计文件及其他技术资料",{"key":22,"text":23,"correct":24},"D","施工队已进场",true,"招标的准备工作包括：(1)按照国家有关规定需要履行项目审批手续的，已经履行审批手续。(2)建设资金或者资金来源已经落实。(3)有满足工程招标需要的设计文件及其他技术资料。(4)法律、法规规定的其他条件。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]