[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91504":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},91504,64,1,"单选题","招标人想把工程建设的资金风险转移给承包商时，一般会采用（）合同。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","成本加利润",false,{"key":16,"text":17,"correct":14},"B","成本加酬金",{"key":19,"text":20,"correct":14},"C","单价",{"key":22,"text":23,"correct":24},"D","总价",true,"总价合同需要投标人按照招标文件的要求，对建设项目报一个总价，合同履行后，工程款的结算以总价作为依据。工程量的风险、物价上涨的风险由承包人承担，适用于工程规模小、工期短和风险不大的房地产开发项目。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]