[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91499":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},91499,64,1,"单选题","关于房地产开发项目质量验收的说法，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分项工程由监理工程师组织施工单位项目专业质量负责人进行验收",false,{"key":16,"text":17,"correct":14},"B","检验批由监理工程师组织施工单位项目专业质量负责人进行验收",{"key":19,"text":20,"correct":14},"C","分部工程由总监理工程师组织施工单位项目负责人等进行验收",{"key":22,"text":23,"correct":24},"D","单位工程由总监理工程师组织施工、设计、监理项目负责人验收",true,"单位工程由施工单位自行组织有关人员进行检查评定，并向建设单位提交工程验收报告；再由建设单位（项目负责人）组织施工(含分包单位)、设计、监理（项目）负责人进行验收。验收合格后，建设单位在规定的时间内将工程竣工验收报告和有关文件报建设行政管理部门备案。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]