[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91469":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},91469,64,1,"单选题","出售型房地产开发项目的计算期是自项目建设开始起至()止的时间。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目竣工验收",false,{"key":16,"text":17,"correct":14},"B","项目经济寿命结束",{"key":19,"text":20,"correct":21},"C","房地产产品全部售完",true,{"key":23,"text":24,"correct":14},"D","业主全部入住","对于出售型房地产开发投资项目，其计算期是从项目建设开始到房地产产品全部售完为止所经历的时间；对于经营型房地产开发投资项目，其计算期是从项目建设开始到项目转售或经济寿命结束所经历的时间；对于置业投资项目，其计算期是从购买时点开始到项目转售或经济寿命结束所经历的时间。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]