[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91393":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},91393,64,2,"多选题","某工程双代号网络计划如下图所示，其关键线路有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","①—②—④—⑥—⑧—⑨",true,{"key":16,"text":17,"correct":14},"B","①—②—⑤—⑥—⑧—⑨",{"key":19,"text":20,"correct":21},"C","①—②—⑦—⑧—⑨",false,{"key":23,"text":24,"correct":14},"D","①—②—④—⑥—⑦—⑧—⑨",{"key":26,"text":27,"correct":14},"E","①—②—⑤—⑥—⑦—⑧—⑨","ABDE","由起点节点到终点节点形成的路线上各项工作持续时间之和最大值所对应的线路就是关键线路，求出备选答案中各线路的持续时间之和，这个和最大的线路即为关键线路。A：9+15+5+5+2=36B：9+14+6+5+2=36C：9+17+2+2=30D：9+15+5+3+2+2=36E：9+14+6+3+2+2=36由此可知选项ABDE的线路均为关键线路。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]