[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91266":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},91266,64,1,"单选题","对建设工程项目目标进行主动控制的主要作用在于( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量检查",false,{"key":16,"text":17,"correct":18},"B","防患于未然",true,{"key":20,"text":21,"correct":14},"C","事中控制",{"key":23,"text":24,"correct":14},"D","进度纠偏","主动控制的主要作用就是通过拟定和采取有针对性的预防性措施，从而减少乃至避免目标偏离，实现防患于未然。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]