[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91262":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},91262,64,1,"单选题","建设工程项目管理目标系统的说法，错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设工程项目管理的目标主要包括质量、投资和进度",false,{"key":16,"text":17,"correct":18},"B","建设工程项目管理目标系统的制定应保证质量、投资和进度均达到最优",true,{"key":20,"text":21,"correct":14},"C","项目的质量、投资和进度之间为对立统一关系",{"key":23,"text":24,"correct":14},"D","项目的质量、投资和进度目标可度量、管理效果可验证","本题考核的是建设工程项目管理目标系统的组成与特点。B选项的错误在于太绝对，管理目标系统的制定不能保证质量、投资、进度均达到最优，这是不现实的，因为三者是相互对立统一的，系统控制是实现三大目标控制的统一，使整个目标系统最优，而不是各项都最优。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]