[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91258":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},91258,64,1,"单选题","落实项目目标控制的组织机构和人员，明确各级目标控制人员的任务和职能分工、权力和责任，制定目标控制的工作流程，这些是建设工程目标控制的( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同措施",false,{"key":16,"text":17,"correct":14},"B","经济措施",{"key":19,"text":20,"correct":14},"C","技术措施",{"key":22,"text":23,"correct":24},"D","组织措施",true,"本题考核的是建设工程目标控制的组织措施内容。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]