[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91248":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},91248,64,1,"单选题","建设工程实施过程中，建设监理对投资实行全过程控制的任务主要集中在( )阶段。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可行性研究、设计和招标",false,{"key":16,"text":17,"correct":18},"B","设计、招标和施工",true,{"key":20,"text":21,"correct":14},"C","可行性研究和施工",{"key":23,"text":24,"correct":14},"D","设计、施工和竣工验收","投资控制的全过程主要是指建设工程实施的全过程，也可以是工程建设的全过程。投资控制主要集中在：①设计阶段、②招标阶段、③施工阶段。因此，B选项是对的。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]