[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91181":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},91181,64,1,"单选题","某城市污水处理工程的建筑安装工程费为2500万元，设备购置费为800万元。根据《建设工程监理范围和规模标准规定》，该工程( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","必须实行监理",true,{"key":16,"text":17,"correct":18},"B","可不实行监理",false,{"key":20,"text":21,"correct":18},"C","仅建筑安装工程实行监理",{"key":23,"text":24,"correct":18},"D","仅设备制造实行监理","该工程的工程费用=2500+800=3300>3000万元，其总投资更是在3000万元以上，属于市政工程项目，故根据《建设工程监理范围和规模标准规定》必须实行监理。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]