[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91139":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},91139,64,1,"单选题","某建设项目现金流量见下表，不考虑资金的时间价值，则该项目的静态投资回收期为( )年。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5．25",false,{"key":16,"text":17,"correct":18},"B","5．72",true,{"key":20,"text":21,"correct":14},"C","6．25",{"key":23,"text":24,"correct":14},"D","6．72","此题考查静态投资回收期的计算。静态投资回收期是指在不考虑资金时间价值条件下，以项目净收益抵偿全部投资所需要的时间。静态投资回收期=(累计净现金流量开始出现正值的年份一1)+上年累计净现值的绝对值／当年净现金流量。故本题中静态投资回收期=6-1+|-402|／560=5．72(年)。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]