[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91024":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},91024,64,1,"单选题","在工程网络计划执行过程中，如果发现某工作进度拖后，则受影响的工作一定是该工作的( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","平行工作",false,{"key":16,"text":17,"correct":18},"B","后续工作",true,{"key":20,"text":21,"correct":14},"C","先行工作",{"key":23,"text":24,"correct":14},"D","紧前工作","进度拖后只能影响其后续工作。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]