[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91023":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},91023,64,1,"单选题","在工程网络计划执行过程中，若某项工作进度比原计划拖后，而拖后的时间未超过其自由时差，则( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总工期及后续工作均不受影响",true,{"key":16,"text":17,"correct":18},"B","不影响后续工作，影响总工期",false,{"key":20,"text":21,"correct":18},"C","不影响总工期，影响后续工作",{"key":23,"text":24,"correct":18},"D","对总工期及后续工作均有影响","自由时差一定小于或等于总时差，所以拖后时间如果未超过自由时差，就一定不会超过总时差，则对总工期及后续工作都没有影响。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]