[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91022":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},91022,64,1,"单选题","在原时标网络计划上，自上而下地从计划执行中某一检查时刻的时标点出发，用点划线依次将各项工作实际进度达到的前锋点连接而成的折线，称为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实际进度曲划线",false,{"key":16,"text":17,"correct":14},"B","实际进度中锋线",{"key":19,"text":20,"correct":21},"C","实际进度前锋线",true,{"key":23,"text":24,"correct":14},"D","实际进度后置线","实际进度前锋线是在原时标网络计划上，自上而下地从计划执行中某一检查时刻的时标点出发，用点划线依次将各项工作实际进度达到的前锋点连接而成的折线。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]