[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91021":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},91021,64,1,"单选题","某网络计划的执行中，检查发现D工作的总时差由3天变成了-1天，则D工作（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工期拖后1天，影响工期1天",false,{"key":16,"text":17,"correct":14},"B","工期拖后3天，影响工期1天",{"key":19,"text":20,"correct":21},"C","工期拖后4天，影响工期1天",true,{"key":23,"text":24,"correct":14},"D","工期拖后4天，影响工期3天","本题考核的是对计划检查结果进行分析判断。总时差=最迟开始时间-最早开始时间，总时差减少了4天，就是工期拖后4天。总时差为-1，说明影响工期1天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]