[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91018":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},91018,64,1,"单选题","在网络计划的检查过程中，发现某工作的实际进度延后了3天，而该工作的总时差和自由时差分别为7天和4天，则此工作的进度拖延（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不影响总工期，但将其后续工作的最早开始时间推迟3天",false,{"key":16,"text":17,"correct":18},"B","既不影响总工期，也不影响其后续工作的正常进行",true,{"key":20,"text":21,"correct":14},"C","将使总工期延长3天，但不影响其后续工作的正常进行",{"key":23,"text":24,"correct":14},"D","将使总工期及其后续工作的最早开始时间均推迟3天","因为该工作的实际进度延后了3天，没有超过该工作的总时差，也没有超过该工作的自由时差，则该工作的进度拖延既不影响总工期，也不影响其后续工作的正常进行。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]