[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91015":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},91015,64,1,"单选题","在单代号网络计划中，某工作的紧后工作最早开始时间的最小值与本工作的最早完成时间之差是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","本工作的自由时差",true,{"key":16,"text":17,"correct":18},"B","紧后工作的自由时差",false,{"key":20,"text":21,"correct":18},"C","本工作与其紧后工作之间的时间间隔",{"key":23,"text":24,"correct":18},"D","本工作的总时差","某工作的紧后工作最早开始时间的最小值与本工作的最早完成时间之差是自由时差。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]