[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91013":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},91013,64,1,"单选题","在单代号网络计划中，工作H的最早开始时间为第12天，持续时间为6天。工作H有三项紧后工作，最早开始时间分别为第22天、24天、26天，则工作H的自由时差是( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4",true,{"key":16,"text":17,"correct":18},"B","6",false,{"key":20,"text":21,"correct":18},"C","8",{"key":23,"text":24,"correct":18},"D","10","（1）工作H的最早完成时间=12+6=18 （2）工作H的自由时差=min(22，24，26)-18=4天",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]