[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91010":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},91010,64,1,"单选题","在单代号网络计划中，某工作与其紧后工作之间的时间间隔应等于( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","该工作紧后工作的最早开始时间与该工作最早开始时间之差",false,{"key":16,"text":17,"correct":14},"B","该工作紧后工作的最迟开始时间与该工作最早完成时间之差",{"key":19,"text":20,"correct":21},"C","该工作紧后工作的最早开始时间与该工作最早完成时间之差",true,{"key":23,"text":24,"correct":14},"D","该工作紧后工作的最迟开始时间与该工作最迟完成时间之差","某工作与其紧后工作之间的时间间隔应等于该工作紧后工作的最早开始时间与该工作最早完成时间之差。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]