[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91008":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},91008,64,1,"单选题","在双代号网络计划中，工作N的持续时间是6天，最早完成时间是第13天，其总时差为5天，则工作N的最迟开始时间是第()天。。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","11",false,{"key":16,"text":17,"correct":18},"B","12",true,{"key":20,"text":21,"correct":14},"C","13",{"key":23,"text":24,"correct":14},"D","18","(1)工作N的最早开始时间=最早完成时间—持续时间=13-6=7(2)工作N的最迟开始时间=工作N的最早开始时间+总时差=7+5=12@##",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]