[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91006":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},91006,64,1,"单选题","双代号网络计划中，工作N的持续时间为5周。其有四项紧后工作，其最迟开始时间分别是第13周、第19周、第21周和第20周，则工作N的最迟开始时间是第（ ）周。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":18},"B","8",true,{"key":20,"text":21,"correct":14},"C","11",{"key":23,"text":24,"correct":14},"D","13","最迟完成时间等于各紧后工作的最迟开始时间LSj—k的最小值。工作N有四项紧后工作，其最迟开始时间分别是第13周、第19周、第21周和第20周，其最小值为第13周。因此，工作N的最迟开始时间为第13周。最迟开始时间等于最迟完成时间减去其持续时间。则工作N的最迟开始时间=13－5=8周。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]