[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91004":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},91004,64,1,"单选题","在网络计划执行过程中，发现工作G尚需5天完成，至该工作最迟完成时间还有3天，则该事项造成的影响是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作G的实际进度比计划进度拖后3天",false,{"key":16,"text":17,"correct":14},"B","工作G的实际进度比计划进度拖后5天",{"key":19,"text":20,"correct":21},"C","将使总工期拖后2天",true,{"key":23,"text":24,"correct":14},"D","将使总工期拖后3天","使总工期拖延的天数=尚需天数-至该工作最迟完成时间=5-3=2天",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]