[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91001":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},91001,64,1,"单选题","工作E有四项紧前工作 A、 B、 C、 D，其持续时间分别为2天、6天、7天、5天，最早开始时间分别为第8天、4天、6天、10天，则工作E的最早开始时间为第（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","12",{"key":19,"text":20,"correct":14},"C","13",{"key":22,"text":23,"correct":24},"D","15",true,"本题考核的是双代号网络计划时间参数的计算。最早开始时间等于各紧前工作的最早完成时间的最大值。A、B、C、D的最早完成时间分别是第10、10、13、15天，所以工作E的最早开始时间为第15天。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]