[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-91000":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},91000,64,1,"单选题","下列关于工作总时差的说法中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总时差是在不影响总工期的前提下，本工作可以利用的机动时间",true,{"key":16,"text":17,"correct":18},"B","总时差是在不影响其后续工作最迟开始时间的前提下，本工作可以利用的机动时间",false,{"key":20,"text":21,"correct":18},"C","总时差是在不影响其后续工作最早完成时间的前提下，本工作可以利用的机动时间",{"key":23,"text":24,"correct":18},"D","总时差是在不影响其紧后工作最早开始时间的前提下，本工作可以利用的机动时间","本题考核的是总时差的定义。总时差，是指在不影响总工期的前提下，本工作可以利用的机动时间。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]