[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90999":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},90999,64,1,"单选题","在网络计划中，工作自由时差与总时差的关系通常是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自由时差=总时差",false,{"key":16,"text":17,"correct":14},"B","自由时差>总时差",{"key":19,"text":20,"correct":14},"C","自由时差≥总时差",{"key":22,"text":23,"correct":24},"D","自由时差≤总时差",true,"在网络计划中，工作自由时差总是小于或等于总时差。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]