[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90997":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},90997,64,1,"单选题","工作A有三项紧后工作 B、 C、 D，其持续时间分别为5天、6天、7天，且 B、 C、D三项工作的最迟完成时间分别为第13天、第15天和第13天，则工作A的最迟完成时间是第( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":18},"B","6",true,{"key":20,"text":21,"correct":14},"C","8",{"key":23,"text":24,"correct":14},"D","9","B工作最迟开始时间＝最迟完成时间-持续时间＝13-5＝8；C工作最迟开始时间＝最迟完成时间-持续时间＝15-6＝9； D工作最迟开始时间＝最迟完成时间-持续时间＝13-7＝6；最迟完成时间等于各紧后工作的最迟开始时间的最小值，则工作A的最迟完成时间=MIN(8,9,6)=6。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]