[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90995":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},90995,64,1,"单选题","在工程网络计划中，工作M的持续时间为5天，其最早开始时间是第6天。该工作有三项紧后工作，最迟开始时间分别为第16天、18天、20天。则工作M的总时差是( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":18},"B","5",true,{"key":20,"text":21,"correct":14},"C","7",{"key":23,"text":24,"correct":14},"D","9","（1）工作M的最早完成时间为：6+5=11 （2）工作M的最迟完成时间为：min（16,18,20）=16 （3）工作M的总时差=其最迟完成时间—其最早完成时间=16-11=5天",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]