[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-90993":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},90993,64,1,"单选题","在双代号时标网络计划中，工作D有四项紧后工作，其工作总时差分别为6周、4周、7周和5周，工作D的自由时差为3周，则工作D的总时差为( )周。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":24,"correct":14},"D","10","由于D不是以终点节点为箭头节点的工作，因此其总时差等于其紧后工作总时差的最小值与本工作的自由时差之和，即4+3=7（周）。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 建筑与房地产经济","经济金融",0]